Newmont/Goldcorp
Electrical design and technologies integration

CHALLENGES AND  SOLUTIONS

The construction and commissioning of the Borden mine posed many challenges for our different teams.

Power Team

The first challenge was to design and engineer the electrical infrastructure of the mine taking into account that the mobile equipment would be electric powered. We wanted to have more underground energy available at a lower cost. The implementation of 1000 volt electrical substations, a first in Canada, has met expectations. It was also necessary to work with the various equipment manufacturers to minimize harmonics on the network.

Telecommunication team

The base of the connected mine goes through the establishment of a reliable and flexible telecommunications network. Our teams had to make it possible to transmit a large amount of information in real time to speed up decision-making and increase worker safety.

Automation team

The project leaders wanted to be able to automate the pumping, the ventilation and the opening of doors or restricted areas.

Electronic team

It was hoped to integrate the IMAGINE mining management platform into operations. Our team has made the deployment scheme and system integration. The different applications used make it possible to better plan shifts and maintenance of vehicles, greatly improve the safety of workers and reduce energy consumption.

Photo gallery


Active in over 15 countries, Meglab delivers practical and cost-effective solutions to meet the industry challenges.

As a specialist in mining technologies, the company has developed trustworthy business relationships and became world known for their integrated solutions.

Facebook

Contact us

The head office

281, 19e rue Val-d'Or
J9P 0L7 (Quebec)

Phone : 819 824-7710 info@meglab.ca

Apply

All rights reserved © 2024 - Meglab | Programmation : LEBLEU